Laying a patio comes down to five stages: set out the area and the levels, dig out, build and compact a sub base, bed each slab on a full bed of mortar with a gentle fall away from the house, then fill the joints. The slabs are the part everyone sees, but the base and the levels are what decide whether a patio stays flat and dry for years or starts rocking and pooling after one winter.
1. Plan the area and the levels
Start by marking out the shape with string lines and pegs. Then work out the finished level. Two rules matter here:
- Stay below the damp proof course. Where the patio meets the house, the finished surface should be at least 150mm below the damp proof course, so rain splashing off the patio cannot bridge it and cause damp inside.
- Build in a fall. The patio should slope gently away from the house so water runs off. A common guide is a fall of around 1 in 60 to 1 in 80, depending on the slab. Our guide to patio drainage goes into this in detail.
Plan steps, walls and raised beds at this stage too. It is far easier to build them in than to add them later.
2. Dig out
Dig out enough depth for the sub base, the bedding layer and the slabs, measured from your finished level. Remove turf, roots and soft soil until you reach firm ground. Soft spots should be dug out further and filled. On clay soil, which is common across much of South East London and Kent, a firm, well compacted base is especially important because clay moves as it wets and dries.
3. Lay and compact the sub base
The sub base is usually a crushed stone material known as MOT type 1. Lay it in layers and compact each layer with a plate compactor, rather than dumping it all in at once. The surface of the sub base should already follow the falls you planned, so the bedding layer is an even thickness all over.
4. Lay the slabs on a full bed
This is where many patios go wrong. Slabs laid on five dabs of mortar leave hollows underneath where water collects, which leads to rocking slabs and staining. We bed every slab on a full mortar bed. Then:
- Lay out the slabs first to check the pattern and the colour mix, especially with natural stone.
- For porcelain, and for many natural stones, brush a priming slurry onto the back of each slab so it bonds to the bed.
- Tap each slab down with a rubber mallet, checking the level and the fall as you go.
- Keep the joints even with spacers and check lines regularly.
5. Fill the joints
Joints can be filled with a traditional mortar, pointed by hand, or with a modern jointing compound brushed in. Porcelain needs a jointing product suited to it. Whatever is used, the joints must be full and neat, because gaps let water under the slabs and give weeds a home. Clean any residue off the surface straight away.
What a DIYer can manage, and when to call a patio builder
A small, flat patio away from the house is a realistic DIY job if you are fit and patient. It is worth calling a patio builder when:
- The patio meets the house and the damp proof course is close to ground level
- The garden slopes and needs steps or retaining walls
- You are laying porcelain, which is hard to cut cleanly and needs a primer
- The area is large, or there is a lot of soil to dig out and take away
Patios with walls and steps built in
As bricklayers, we build the steps, retaining walls, raised beds and seating walls that go with a patio as part of the same job. See our patios page, or our Indian sandstone patios if you like a natural stone look. Wondering what drives the price? Read our patio cost guide.
We are based in Bexleyheath and lay patios across Beckenham, Sidcup and the areas around them. Ask for a free written quote and Ricky will come out to look at your garden.